If FCR is presented, there are usually three dates, cargo received date, shipped on board and date of issue. All of them can differ from each other. Which one should be judged as date of shipment if the L/C does not stipulate?

User avatar
picant
Posts: 2026
Joined: Wed Aug 20, 2008 1:49 pm

Forwarder's certificate of receipt

Post by picant » Fri Feb 12, 2010 9:25 pm

Hi Pal,

as per point 19 ISBP 681 FCR is not a carrier type transport document, so if called for in an l/c it must be expressely stated the date required. e.g. in field 48 MT700 : Documents must be presented within 21 days from the date of Issuance / or on board notation/ or goods taking up of FCR